Case Studies

Shutdown Services

Right Left
  • Pic_19._Completed_works_new_grizzly_installed._450450

    Vibrating Grizzly Change Out & Feed Chute Repair

    Location: Eastern Pilbara Mine Site Project goal: Replace the existing vibrating grizzly and repair existing feed chute. The primary crusher received extensive damage when...
    More Info
  • Removing_jaw_crusher_rock_guard_450450

    Primary Rebuild Project - Area C Mine Site

    Project Duration: Five days. Job Scope Linkforce were contracted to undertake a series of projects within the primary area of OHP1, at Area C. Overall the project was...
    More Info
  • rotating_apron_feeder_to_locate_split_in_drive_chain_450450

    Apron Feeder Change Out - Yandicoogina

    Project Duration: Five days Job Scope Linkforce Engineering Shutdown Operations were contracted to plan and implement a safe and effective means of removing and replacing...
    More Info
  • Pic.9-Screen-lowered-into-final-position._450450

    Screen Change Out - Yandicoogina

    Duration: 3 days Job Scope Project requirements were to lift out and replace vibrating screen and any other works with in the area as part of scheduled shutdown maintenance...
    More Info

Capital Works Projects

Right Left
  • IMG_19271_web_450450

    Yandicoogina Fixed Plant Workshop

    The Yandi Fixed Plant Workshop Project was undertaken on behalf of Rio Tinto as a design and construct contract. The site is in a remote location approximately 80km North West...
    More Info
  • Parallel_Poly_pipes_450450

    Waste Water Treatment Plant Upgrade - Mesa J Minesite

    Project Duration: 34 days Scope and associated challenges The project scope was to install a Biomax Waste Water Treatment Plant (WWTP) to service the administration and...
    More Info
  • Linkforce_Excavator_450450

    Waste Fines Polypipe Project - Yandicoogina

    Project Duration: Six weeks Job Scope Linkforce Projects and Construction division were given the task of designing and constructing a 7km Polypipe system for the...
    More Info
  • Pic-5.-Site-Tie-In-Works_450450

    108 Room Install - Yandicoogina

    Project Duration: Three months Project Scope Install an additional 108 rooms and associated services, including Common Rooms, Laundry Facilities, Landscaping and...
    More Info
  • YandiCampBeerGarden_450450

    Yandicoogina Sustaining Project - Infrastructure Upgrade

    The Yandi Sustaining Project was a significant design and construct contract completed over 24 months across multiple work fronts within the Rio Tinto Yandicoogina Mine...
    More Info

Access Scaffolding

Right Left
  • pic2_450450

    Rom Beam Repairs - Brockman 4

    During a 36 hour shutdown Linkforce were required to remove existing ROM beams for the installation of Bump Stomps and remedial works to ROM beam dampers. The tool time allocated...
    More Info

Maintenance Projects

Right Left
  • Fixed Price Operational Project 02

    Fixed Price Operational Project

    The Fixed Price Operational Project scope called for the refurbishment of a Dual Apron Feeder along with the refurbishment of all the running modules on the Dual Car Dumper....
    More Info