Yandicoogina YCV213 Conveyor Truss Replacement Works

Jul 28
1 min read

Updated: Jul 30




Client Rio Tinto


Service  Project Delivery


Location Western Australia



Market

Mining & Industrial


Commodity Iron Ore


Overview

Linkforce delivered the replacement of two critical conveyor truss structures supporting Conveyor YCV213 at Rio Tinto's Yandicoogina mine. The project involved the fabrication, transport and installation of new 18m and 27m truss modules, alongside associated civil, structural, mechanical and electrical works, to restore the long-term integrity and reliability of this key ore handling asset.


Delivered through an integrated approach spanning fabrication, logistics, installation and commissioning, the works were completed within a planned shutdown environment.



Service Delivery Area 

  • Mechanical & Structural

  • Electrical & Instrumentation

  • Civil Construction

  • Fabrication

  • Access Solutions

  • Pipeline Construction

  • Transport & Logistics


Value Added 

  • Experienced project team with proven capability delivering complex brownfield infrastructure upgrades

  • In-house fabrication capability, delivering 111 tonnes of structural steel fabrication

  • Integrated delivery model spanning fabrication, logistics, installation and commissioning

  • Agile execution approach that enabled rapid response to site, logistics and constructability challenges

  • Strong supplier and subcontractor partnerships supporting specialised transport, lifting and installation activities

  • Certified management systems aligned with ISO 9001, ISO 14001 and ISO 45001 standards


Outcome 

Linkforce successfully completed the fabrication, transport, installation, commissioning and handover of two replacement conveyor truss structures supporting Conveyor YCV213. Supported by 111 tonnes of structural steel fabrication and associated civil, mechanical, electrical and access works, the project was delivered within the scheduled shutdown window while minimising operational disruption. The completed works restored the structural integrity of a critical ore handling asset, improving reliability, extending service life and supporting the safe and efficient movement of ore through the processing circuit.